Home   News   Article

Massive £400 million plan to replace Fort Augustus to Skye pylon line progresses


By Neil MacPhail

Register for free to read more of the latest local news. It's easy and will only take a moment.



Click here to sign up to our free newsletters!
Bright new future for pylon line to west.
Bright new future for pylon line to west.

PLANS costing around £400 million to replace the Fort Augustus to Skye electricity transmission line have taken a major step forward.

The GB energy regulator, Ofgem, has confirmed the move, recognising the clear need for the project which will pave the way to progressing the Final Needs Case stage of the regulatory approvals process.

Following not long after the UK Government’s Energy Security Strategy, the Skye reinforcement project will secure future electricity supplies in the area and enable the growth in renewables, supporting the transition to net zero emissions and helping secure the country’s future energy independence, says SSE.

The project is one of the most significant energy investments in the West Highlands since power was first brought to the area in the 1950’s.

SSE added: "This investment will unlock hundreds of skilled jobs throughout the construction phase and many more throughout the supply chain and wider economy, providing a major boost to local and national economies."

Rob McDonald, managing director of SSEN Transmission, said: “We welcome Ofgem’s confirmation that the Skye reinforcement project is needed to help meet the future energy needs in the area.

"We also welcome Ofgem’s commitment to allow flexibility in the timing of its final assessment of our proposals, allowing regulatory and planning processes to be undertaken in parallel to avoid unnecessary delays in delivery.

“The replacement of the Fort Augustus-Skye overhead line will be one of the most significant energy investments in the West Highlands since the original line was installed from the 1950’s onwards, unlocking hundreds of skilled jobs and providing a significant economic boost to local and national economies.

"We are really excited to build on our heritage of powering the highlands and islands as we continue to deliver a network for net zero emissions and secure future electricity supplies across the north of Scotland.”

“We now look forward to working constructively with Ofgem and wider stakeholders as we progress with the Final Needs Case to take forward our proposed solution.”

The Final Needs Case remains on track to be submitted to Ofgem for regulatory approval in August which will then be followed by the Project Assessment, which will determine the level of investment requirement for the project.

SSEN Transmission’s investment in the Skye reinforcement project is part of the SSE Group’s Net Zero Acceleration Programme, which will see £12.5bn invested in the five years to 2026, or £7 million every day. SSEN Transmission alone expects to invest around £4bn over this period as it delivers a network for net zero in the north of Scotland.

The existing Fort Augustus-Skye overhead line is fast approaching the end of its operational life and is in urgent need of intervention.

Its planned replacement is therefore essential to maintain network reliability and security of supply to homes and businesses along its route, as well as to the Western Isles, which is primarily supplied by two subsea cables from Ardmore point.

To enable the connection of new renewable electricity along the route, SSEN Transmission is proposing to increase the capacity of the replacement line, supporting the UK and Scottish Governments transition to net zero emissions. The existing line has already exceeded its capacity limit, preventing the connection of new renewable electricity in the area.

SSEN Transmission expects to submit its planning application to Scottish Ministers this summer.

As part of this and in response to stakeholder feedback, SSEN Transmission is actively assessing the potential for undergrounding as the line passes the Cuillin Hills and where it connects to Fort Augustus substation; and alternative routes as it passes Kylerhea.

Separately, work to progress a 600MW HVDC connection to the Western Isles continues with SSEN Transmission committed to continuing to work constructively with Ofgem, Government, Western Isles generators and wider stakeholders to overcome barriers to unlock the Western Isles vast renewables potential.


Do you want to respond to this article? If so, click here to submit your thoughts and they may be published in print.



This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies - Learn More